16 women can do the work in =12 days
1 women can do the work in = (1612) days
1 women can in 1 days = part of the work
Again, 12 men can do the work in = 8 days
1 man can do the work in = (8 12) days
I man can in 1 days = part of the work
16 men's 3 day's work = part of the work
Remaining work =
Now, number of men still working = 16-10=6
6 men's 1 days work = part
And 4 men's 1 days work =part
They can do in 1 day = part
Now, part of the work is done in = 1 day
part of the work is done in = = 6 days.