Consider the following two mutually exclusive projects, each of which require an initial investment of Tk. 100,000 and have no salvage value. This organization, which has a cost of capital of 15%, must choose one or the other.

YearProject AProject B
1Tk. 10,00020,000
220,00040,000
330,00030,000
440,00020,000
550,00010,000

Compute the payback period of these two projects. Using the payback. criterion, which project is more desirable?

Updated: 11 months ago
উত্তরঃ

Project A: Payback Period Calculation

Initial Investment = Tk. 100,000

    

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                      
YearCash Flow (Tk.)Cumulative Cash Flow (Tk.)
110,00010,000
220,00010,000 + 20,000 = 30,000
330,00030,000 + 30,000 = 60,000
440,00060,000 + 40,000 = 100,000
550,000100,000 + 50,000 = 150,000

From the table, the cumulative cash flow reaches Tk. 100,000 at the end of Year 4.

Therefore, Payback Period for Project A = 4 years.


Project B: Payback Period Calculation

Initial Investment = Tk. 100,000

    

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                      
YearCash Flow (Tk.)Cumulative Cash Flow (Tk.)
120,00020,000
240,00020,000 + 40,000 = 60,000
330,00060,000 + 30,000 = 90,000
420,00090,000 + 20,000 = 110,000
510,000110,000 + 10,000 = 120,000

At the end of Year 3, the cumulative cash flow is Tk. 90,000. The remaining amount to be recovered is:

Remaining Investment = Initial Investment - Cumulative Cash Flow at Year 3

Remaining Investment = Tk. 100,000 - Tk. 90,000 = Tk. 10,000


The cash flow in Year 4 is Tk. 20,000.

Fraction of Year 4 required to recover the remaining investment = Remaining Investment / Cash Flow in Year 4

Fraction = \( \frac{10,000}{20,000} = 0.5 \) years


Therefore, Payback Period for Project B = 3 years + 0.5 years = 3.5 years.


Conclusion: Desirability using Payback Criterion

Payback Period for Project A = 4 years

Payback Period for Project B = 3.5 years


According to the payback period criterion, the project with the shorter payback period is considered more desirable because it recovers the initial investment faster, thus reducing risk. In this case, Project B has a shorter payback period (3.5 years) compared to Project A (4 years).

Therefore, using the payback criterion, Project B is more desirable.

Satt AI
Satt AI
7 hours ago
503

Related Question

View All
শিক্ষকদের জন্য বিশেষভাবে তৈরি

১ ক্লিকে প্রশ্ন, শীট, সাজেশন
অনলাইন পরীক্ষা তৈরির সফটওয়্যার!

শুধু প্রশ্ন সিলেক্ট করুন — প্রশ্নপত্র অটোমেটিক তৈরি!

প্রশ্ন এডিট করা যাবে
জলছাপ দেয়া যাবে
ঠিকানা যুক্ত করা যাবে
Logo, Motto যুক্ত হবে
অটো প্রতিষ্ঠানের নাম
অটো সময়, পূর্ণমান
প্রশ্ন এডিট করা যাবে
জলছাপ দেয়া যাবে
ঠিকানা যুক্ত করা যাবে
Logo, Motto যুক্ত হবে
অটো প্রতিষ্ঠানের নাম
অটো সময়, পূর্ণমান
অটো নির্দেশনা (এডিটযোগ্য)
অটো বিষয় ও অধ্যায়
OMR সংযুক্ত করা যাবে
ফন্ট, কলাম, ডিভাইডার
প্রশ্ন/অপশন স্টাইল পরিবর্তন
সেট কোড, বিষয় কোড
অটো নির্দেশনা (এডিটযোগ্য)
অটো বিষয় ও অধ্যায়
OMR সংযুক্ত করা যাবে
ফন্ট, কলাম, ডিভাইডার
প্রশ্ন/অপশন স্টাইল পরিবর্তন
সেট কোড, বিষয় কোড
এখনই শুরু করুন ডেমো দেখুন
৫০,০০০+
শিক্ষক
৩০ লক্ষ+
প্রশ্নপত্র

Related Question

মাত্র ১৫ পয়সায় প্রশ্নপত্র
১ ক্লিকে প্রশ্ন, শীট, সাজেশন তৈরি করুন আজই

Complete Exam
Preparation

Learn, practice, analyse and improve

1M+ downloads
4.6 · 8k+ Reviews