The cost of a project is Tk. 50,000 and it generates cash inflows of Tk. 20,000, Tk. 15,000, Tk. 25,000, and Tk. 10,000 over four years. Using the present value index method, appraise the profitability of the proposed investment, assuming a 10% rate of discount.
Created: 11 months ago
|
Updated: 3 months ago
The cost of a project is Tk. 50,000 and it generates cash inflows of Tk. 20,000, Tk. 15,000, Tk. 25,000, and Tk. 10,000 over four years. Using the present value index method, appraise the profitability of the proposed investment, assuming a 10% rate of discount.
Asked by
MD Tipu Hossain
MD Tipu Hossain