If Masud can do a job in P days, while Minhaz can do the same job in Q days separately, how long will it take to finish the job if they work together?
If Masud can do a job in P days, while Minhaz can do the same job in Q days separately, how long will it take to finish the job if they work together?
-
ক
(P+Q)/PQ days
-
খ
PQ/(P+Q) days
-
গ
(P+Q) days
-
ঘ
(1/P + 1/Q) days
In P days Masud can do = 1 job
∴ In 1 day Masud can do = part of the job
In Q days Minhaz can do = 1 job
∴ In 1 day Minhaz can do = part of the job
In 1 day together they can do = part of the job
Now, part of the job can do in = 1 day
∴ Now total part of the job can do in day
Using direct & Indirect proportion
If m men do work in p days
then (m+r) men can do work in mp/m+r days
Masud alone can do a job in P days
So, Masud's 1 day's work = 1/P
Minhaz alone can do a job in Q days
So, Minhaz's 1 day's work = 1/Q
In 1 day, Masud and Minhaz can do together = (1/P+1/Q) = (Q+P)/PQ part of the job
Now,
(Q+P)/PQ part of the job can be finished in 1 day
So, 1 part of the job can be finished in 1÷(Q+P)/PQ days = PQ/(P+Q) days.
Related Question
View All-
ক
২৪
-
খ
২৫
-
গ
২৮
-
ঘ
৩০
-
ঙ
কোনটিই নয়
-
ক
১২
-
খ
৮
-
গ
৭
-
ঘ
৬
-
ঙ
কোনটিই নয়
অপু, দীপু, নিপু একটি কাজ যথাক্রমে ৬, ১০, ১৫ দিনে করতে পারে। একত্রে তারা কাজটি কত দিনে করতে পারবে?
-
ক
১২ দিন
-
খ
১ দিন
-
গ
৬ দিন
-
ঘ
৩ দিন
-
ক
৩০
-
খ
২৫
-
গ
২০
-
ঘ
৩৫
-
ক
২৫ দিনে
-
খ
৩০ দিনে
-
গ
৩৫ দিনে
-
ঘ
৪০ দিনে
-
ক
২৪ জন
-
খ
১৬ জন
-
গ
১২ জন
-
ঘ
৮ জন