A group of workers can do a piece of work in 24 days. However as 7 of them were absent it took 30 days to complete the work. How many people actually worked on the job to complete it?
A group of workers can do a piece of work in 24 days. However as 7 of them were absent it took 30 days to complete the work. How many people actually worked on the job to complete it?
Created: 6 months ago |
Updated: 2 months ago
Updated: 2 months ago
-
ক
35
-
খ
30
-
গ
28
-
ঘ
42
উত্তরঃ
Let, number of workers = x
x person complete their works = 24 days
∴ “ ” “ ” = 24x "
∴(x-7) “ ” " = "
so
30x - 210 = 24x
Sumaiya Mim
2 months ago
Related Question
View All
Created: 1 day ago |
Updated: 1 day ago
Updated: 1 day ago
-
ক
সমকোণী
-
খ
সূক্ষ্মকোণী
-
গ
স্থূলকোণী
-
ঘ
সমবাহু
Created: 1 day ago |
Updated: 1 day ago
Updated: 1 day ago
-
ক
c + b
-
খ
a + c
-
গ
ac
-
ঘ
c - b
Created: 1 day ago |
Updated: 1 day ago
Updated: 1 day ago
-
ক
৫০০
-
খ
৪২০
-
গ
৬৬০
-
ঘ
৪১০
শিক্ষকদের জন্য বিশেষভাবে তৈরি
১ ক্লিকে প্রশ্ন, শীট, সাজেশন ও
অনলাইন পরীক্ষা তৈরির সফটওয়্যার!
শুধু প্রশ্ন সিলেক্ট করুন — প্রশ্নপত্র অটোমেটিক তৈরি!
প্রশ্ন এডিট করা যাবে
জলছাপ দেয়া যাবে
ঠিকানা যুক্ত করা যাবে
Logo, Motto যুক্ত হবে
অটো প্রতিষ্ঠানের নাম
অটো সময়, পূর্ণমান
প্রশ্ন এডিট করা যাবে
জলছাপ দেয়া যাবে
ঠিকানা যুক্ত করা যাবে
Logo, Motto যুক্ত হবে
অটো প্রতিষ্ঠানের নাম
অটো সময়, পূর্ণমান
অটো নির্দেশনা (এডিটযোগ্য)
অটো বিষয় ও অধ্যায়
OMR সংযুক্ত করা যাবে
ফন্ট, কলাম, ডিভাইডার
প্রশ্ন/অপশন স্টাইল পরিবর্তন
সেট কোড, বিষয় কোড
অটো নির্দেশনা (এডিটযোগ্য)
অটো বিষয় ও অধ্যায়
OMR সংযুক্ত করা যাবে
ফন্ট, কলাম, ডিভাইডার
প্রশ্ন/অপশন স্টাইল পরিবর্তন
সেট কোড, বিষয় কোড
Related Question
মাত্র ১৫ পয়সায় প্রশ্নপত্র
১ ক্লিকে প্রশ্ন, শীট, সাজেশন তৈরি করুন আজই
Question Analytics
মোট উত্তরদাতা
জন
সঠিক
ভুল
উত্তর নেই