If 17 labourers can dig a ditch 26 m long in 18 days, working 8 hours a day; how many more labourer working 9 hours a day?
-
ক
34
-
খ
51
-
গ
68
-
ঘ
85
Given:
- 17 laborers can dig a ditch 26 meters long in 18 days, working 8 hours a day.
First, calculate the total man-days required for this task: Total man-days = (Number of laborers) × (Number of days) = 17 × 18 = 306 man-days.
Now, we want to find out how many more laborers are needed if they work 9 hours a day. Let's denote the number of additional laborers needed as "x."
In this case, the total man-days required to complete the same task with 9 hours of work per day would remain the same (306 man-days).
So, we can set up the equation: (17 + x) laborers × 9 hours per day = 306 man-days
Now, solve for x:
17x + 9x = 306 26x = 306 x = 306 / 26 x = 51
So, 51 more laborers are needed if they work 9 hours a day to complete the same task.
The correct answer is 51.
Related Question
View All-
ক
২৪
-
খ
২৫
-
গ
২৮
-
ঘ
৩০
-
ঙ
কোনটিই নয়
-
ক
১২
-
খ
৮
-
গ
৭
-
ঘ
৬
-
ঙ
কোনটিই নয়
অপু, দীপু, নিপু একটি কাজ যথাক্রমে ৬, ১০, ১৫ দিনে করতে পারে। একত্রে তারা কাজটি কত দিনে করতে পারবে?
-
ক
১২ দিন
-
খ
১ দিন
-
গ
৬ দিন
-
ঘ
৩ দিন
-
ক
৩০
-
খ
২৫
-
গ
২০
-
ঘ
৩৫
-
ক
২৫ দিনে
-
খ
৩০ দিনে
-
গ
৩৫ দিনে
-
ঘ
৪০ দিনে
-
ক
২৪ জন
-
খ
১৬ জন
-
গ
১২ জন
-
ঘ
৮ জন
১ ক্লিকে প্রশ্ন, শীট, সাজেশন ও
অনলাইন পরীক্ষা তৈরির সফটওয়্যার!
শুধু প্রশ্ন সিলেক্ট করুন — প্রশ্নপত্র অটোমেটিক তৈরি!
Related Question
Question Analytics
মোট উত্তরদাতা
জন